Thanks Robert! I had been waiting for FHWA to post the link before I made my blog post, and had not checked in a couple of weeks. I was taking a quick look here to catch up and saw your post, which really worked out great. Great job! As far as I know, it is not in a Spanish version at this time. Hi Robert I could translate in Spanish from chapter 4 to 7 but I would like conpararlo with another person who has also translated to verify that there is error in the translation, it would be helpful to consult the FHWA.

News Ticker. Comings and Goings. Share this:. My friend, Randy Post, has an outside review meaning not connected to one of the authors! The biggest change is completely re-writing the design sections to follow LRFD as well as to update the methods for calculating soil and rock resistance.

Make sure and go read his review, as well as check out the other things on his blog disclosure by Robert: I am an occasional contributor there. Brown, Ph. Turner, Ph. If drilled shafts are to be tipped in very hard material that is overlain by soft strata, the skin friction contribution of the softer strata may be disregarded in design.

However, do not ignore the contribution of significant amounts of competent material in order to tip in rock. In many areas of the state, rock is overlain by thick layers of material that can support considerable loads. Belled drilled shafts are no longer used as a foundation element for bridge foundations. Therefore, do not use belled shafts for bridge foundation design.

Drilled shafts installed in lakes or rivers require use of a casing placed from above the water surface to a minimum embedment into the river or lake bottom. Do not define the top of the drilled shaft in the normal manner a set distance below finished grade.

Define the top of the drilled shaft as 1 to 2 ft. If the water level is variable, add a provision allowing the top of the drilled shaft to be adjusted based on water level at the time of construction.

Allow casing required for construction to remain in place at the option of the contractor. Typically, casings left in place look no worse than the stained concrete shaft that will be visible if casings are removed. If casing is to be left in place, disregard skin friction along the length of the casing. If permanent casing is used in standing water, consideration should be given to painting the portion of casing extending above the mud line.

Found wing shafts in similar founding material as abutment shafts to minimize the potential for differential settlement. See the following table for maximum drilled shaft service loads recommended without conducting a detailed structural analysis.